We are looking at a job that is requiring Basket tray. Its the type sold by Cablofil, B-line, and Wiremold. I love the stuff as it is very easy to bend and install. You just cut it and bend it how every you like. The Cablofil product actually has great literature as well. Does anybody have a good labor unit number for this type of product? All my estimation programs use cable tray as a description. These number look pretty high. I am not sure how long basket tray has been on the market, I myself have only started using it in the last year. Also, the numbers I am seeing for pulling data wire, ( UTP, Cat 5E, 6) seem a little high as well. Does anybody have good solid numbers for each?? This estimation would be for pulling wire in the basket and then into conduits bonded to the tray

Thanks in Advance!
 
Re: Estimation on Basket tray and pulling the data wire in i

Hi trying hard.
Are you saying 9 hours per 1000 feet for pulling in wire?
 
Re: Estimation on Basket tray and pulling the data wire in i

Yep; and I would be really careful to ever go below this. If you have short, and few, drops use 10. M :)
 
Status
Not open for further replies.
Top