B bwyllie Senior Member Location MA Dec 28, 2006 #1 an existing pool is being infilled to make it a shallower pool. the new structure/flooring will need to be bonded as per NEC, how do we confirm that the existing pool structure is bonded? Last edited: Dec 28, 2006
an existing pool is being infilled to make it a shallower pool. the new structure/flooring will need to be bonded as per NEC, how do we confirm that the existing pool structure is bonded?
Tori Senior Member Location Maryland Dec 28, 2006 #2 chip up the bottom untill you get to the rebar and get some long leads and test it
E edamico11 Senior Member Location NJ Dec 28, 2006 #3 I agree with Tori, it may take some work,, but it is the only way to be sure IMO.