larrykinne
Member
At what point as an inspector due you say change the whole service? I have had people with a old pull out fuse block panel with the meter in the basement move the meter out side and replace the seu from the w/h down and into the old panel and say that is exsisting! also they have done it with split buss panels and main lug panels. I tell them to install a new m/b panel. The state of NY tells me i'm wrong, am I?