I have a project with a 5MVA xfmr on a deck beside a building. I need to bring the secondary 5KV cables (2-500mcm per phase 1200A) from the transformer into a metal interlocking building and supply power to 5KV SWGR. My question is how to run these cables. I had planned to use ladder type alum cable tray. My questions is do I need any thing special for the tray like totally enclosed or at lease a cover to present UV from hitting the cables all the time.
This project is for a power plant in Arizona.
Thanks in advance for any advice!
This project is for a power plant in Arizona.
Thanks in advance for any advice!