EIT42
New member
- Location
- Houston, Texas, USA
I was wondering if anyone could comment on whether or not a permit is required and whether the work in the following 2 scenarios must be done by a licensed electrician.
Scenario 1:
We want to install new equipment at an outdoor location approximately 300 feet from the closest 480V 3 phase supply in the factory grounds. The new equipment would require about 43A. We have an existing breaker already available in the board, that used to supply power to equipment that is now redundant on no longer in service. This will require digging a trench of about 280 feet from the existing breaker to the disconnect switch for the new equipment. I was thinking of running the cable (oversized to factor in voltdrop) in a PVC conduit, buried about 3 feet deep. First question: is this deep enough or is this too deep? Or should I use galvanized pipe?I plan on calling the 811 number to mark any buried utilities in the area, and hire an independent company to use ground penetrating radar to evaluate if there is any factory utilities beneath the area were the trench is planned. We have factory electricians, but they are very busy, and not licensed. But if we used our electricians, could we do this job ourselves withing needing to pull a city permit, or have inspections done? Does NEC treat factory installations a little different for residential installations? Obviously we will follow factory lockout procedures for this. Would that be adequate. We're also thinking of having a local contractor to the full turn key (dig the trench, install pipe and cable and connect). If we used a contractor, would they need to pull a city permit, or use a licensed electrician?
Scenario 2:
On the opposite side of the factory, we plan to install a second piece of equipment. There is no nearby 480V source, but there is a nearby factory owned 34.5kV overhead line. The metered utility interconnect that this overhead line connects to is several hundred feet away and has a pole mounted disconnect switch on our side (and utility side). Could we install 3 cluster mounted pole PT's (obviously following the factories lock out tag out procedures), or perhaps a small pad mount transformer connected to our nearby overhead line, without requiring to draw a city permit, and do the work with our unlicensed electricians? Like wise if we used a contractor, could they do the work without needing to draw a city permit or use a licensed electrician? Due to redundant equipment that will no longer run, we already know that the line is sized more than adequately for this new installation.
The above questions are more about the legalities than the technical requirements. I would appreciate your feedback on this.
Oh - This is for an installation in Houston Texas.
Scenario 1:
We want to install new equipment at an outdoor location approximately 300 feet from the closest 480V 3 phase supply in the factory grounds. The new equipment would require about 43A. We have an existing breaker already available in the board, that used to supply power to equipment that is now redundant on no longer in service. This will require digging a trench of about 280 feet from the existing breaker to the disconnect switch for the new equipment. I was thinking of running the cable (oversized to factor in voltdrop) in a PVC conduit, buried about 3 feet deep. First question: is this deep enough or is this too deep? Or should I use galvanized pipe?I plan on calling the 811 number to mark any buried utilities in the area, and hire an independent company to use ground penetrating radar to evaluate if there is any factory utilities beneath the area were the trench is planned. We have factory electricians, but they are very busy, and not licensed. But if we used our electricians, could we do this job ourselves withing needing to pull a city permit, or have inspections done? Does NEC treat factory installations a little different for residential installations? Obviously we will follow factory lockout procedures for this. Would that be adequate. We're also thinking of having a local contractor to the full turn key (dig the trench, install pipe and cable and connect). If we used a contractor, would they need to pull a city permit, or use a licensed electrician?
Scenario 2:
On the opposite side of the factory, we plan to install a second piece of equipment. There is no nearby 480V source, but there is a nearby factory owned 34.5kV overhead line. The metered utility interconnect that this overhead line connects to is several hundred feet away and has a pole mounted disconnect switch on our side (and utility side). Could we install 3 cluster mounted pole PT's (obviously following the factories lock out tag out procedures), or perhaps a small pad mount transformer connected to our nearby overhead line, without requiring to draw a city permit, and do the work with our unlicensed electricians? Like wise if we used a contractor, could they do the work without needing to draw a city permit or use a licensed electrician? Due to redundant equipment that will no longer run, we already know that the line is sized more than adequately for this new installation.
The above questions are more about the legalities than the technical requirements. I would appreciate your feedback on this.
Oh - This is for an installation in Houston Texas.