J Joao Member Location portugal Occupation engineer Mar 19, 2025 #1 For a FEED stage do you know which are the minimum deliverables documents (written, drawings and calculations) needed? Is there any standard/rule for it?
For a FEED stage do you know which are the minimum deliverables documents (written, drawings and calculations) needed? Is there any standard/rule for it?
Jraef Moderator, OTD Staff member Location San Francisco Bay Area, CA, USA Occupation Electrical Engineer Mar 19, 2025 #2 It’s usually something that the FEED study provider quotes up front, or the customer defines in their RFP. In fact it’s often a negotiating point.