New EE
Member
- Location
- California
I have this dilema where I have a 225A feeder ( 2 1/2"C, 4 #4/0, 1 #4 GRD) feeding a panelboard. The problem is that a 2" conduit was ran underground when they poured the slab. (The original feeder was smaller, then more equipment was added on this panel so I had to increase the amperage). There is actually two 2" empty conduits but I believe the feeder has to run in the same conduit if I'm not mistaken. The structure is already up and they are just building out the space now so we can't run a new feeder overhead being that the electrical room is not attached to the structure. Appreciate any suggestions on how to rectify this situation. Thanks.