102 Inspector
Senior Member
- Location
- N/E Indiana
- Occupation
- Inspector- All facets
As a small town inspector, I am having trouble finding chapter and verse to support or deny an installation. Owner has a feeder from a disconnect that runs underground to a building approximately 300 feet away. He would like to install a tap onto this line to serve a second building and cutting the run length of a new feeder. The load calculations are no where near maxed out when considering both buildings. Can he install a splice box in the ground and tap off the feeder or does he need to run new feeders from the disconnect to the newly proposed building? Hope this make sense.