If I come out of a main breaker load side and I go 75', can I install a wire way and tap that feeder. Do I need over current protection before I tap the feeders?
OK I'm going to try this new format. If you are using the correct terminology, you may go 75 feet and then tap the "feeder". This of course is indicating you are following the 240.21 feeder tap rules and it is indeed a feeder.