There are waytoo may fire pump questions on this forum, so I figured I would ask a few more.I just can't find an answer to my application. Plus, I haven't sized a servicefor a fire pump in quite a while, so I'm a little rusty.
I'm bringing a single service to the building. I want to tap ahead of the main(after the utility meter) and feed the pump. The tap will be in a separatevertical section and it will feed the fire pump controller. I will specify thefeeders to be run under slab to the fire pump room.
So here are few questions:
It's just a tap feeding the controller. The NEC does not require an OCPD at theswitchboard?
Feeders should be 125% FLA of the motor?
Can the utility meter and the fire pump tap be in the same vertical section, ormust it be dedicated?
When sizing the service feeders, do I need to include the FLA of the fire pumpplus the service amperage?
Do the feedersfrom the utility transformer to the main switchboard need to be concreteencased, or rated for 2 hours?
Thanks
I'm bringing a single service to the building. I want to tap ahead of the main(after the utility meter) and feed the pump. The tap will be in a separatevertical section and it will feed the fire pump controller. I will specify thefeeders to be run under slab to the fire pump room.
So here are few questions:
It's just a tap feeding the controller. The NEC does not require an OCPD at theswitchboard?
Feeders should be 125% FLA of the motor?
Can the utility meter and the fire pump tap be in the same vertical section, ormust it be dedicated?
When sizing the service feeders, do I need to include the FLA of the fire pumpplus the service amperage?
Do the feedersfrom the utility transformer to the main switchboard need to be concreteencased, or rated for 2 hours?
Thanks