Hello every one...
We are in the process of designing a data center, this project has two separate normal power sources, A & B (13.8KV) and the whole building is backed up by 4 generators (13.8KV), N+1 configuration. There are two fire pumps (one is redundant), the thought is to provide two transformers (13.8KV pri- 480V Sec) for each fire pump. One transformer will powered from the normal 13.8KV switchgear (source A) and the other transformer will be powered from the generator MV paralleling switchgear. At the secondary of the transformers, each will have two feeders; each will feed each of the fire pump via ATS/Controller. My question, does this meet the requirement of the NEC section 695? Do I have to tap a head of the main normal service disconnect (at the transfromer) for this installation in lieu powering it from a feeder breaker? Anythoughts....
Thanks,
We are in the process of designing a data center, this project has two separate normal power sources, A & B (13.8KV) and the whole building is backed up by 4 generators (13.8KV), N+1 configuration. There are two fire pumps (one is redundant), the thought is to provide two transformers (13.8KV pri- 480V Sec) for each fire pump. One transformer will powered from the normal 13.8KV switchgear (source A) and the other transformer will be powered from the generator MV paralleling switchgear. At the secondary of the transformers, each will have two feeders; each will feed each of the fire pump via ATS/Controller. My question, does this meet the requirement of the NEC section 695? Do I have to tap a head of the main normal service disconnect (at the transfromer) for this installation in lieu powering it from a feeder breaker? Anythoughts....
Thanks,