quick question on the fire pump
we have a piece of switchgear that has five sections
first section is the incoming sec
second is the meter and main section
and we have a utility transformer, feeds coming underground to the building, running outside
up and then in through a wall to the switchgear, checking nec 695.3(1)
my question is, the five sections are considered the inclosure, so the splice for the firepump
has to be outside the five sections
the swithgear is on the mezzanine level
the firepump is on the first level
so where the underground (we have 6-4" conduits for 2400amp)comes up on the
outside wall, that would be where we get our power for the firepump
does the feed have to be metered for the utility
thanks as always
we have a piece of switchgear that has five sections
first section is the incoming sec
second is the meter and main section
and we have a utility transformer, feeds coming underground to the building, running outside
up and then in through a wall to the switchgear, checking nec 695.3(1)
my question is, the five sections are considered the inclosure, so the splice for the firepump
has to be outside the five sections
the swithgear is on the mezzanine level
the firepump is on the first level
so where the underground (we have 6-4" conduits for 2400amp)comes up on the
outside wall, that would be where we get our power for the firepump
does the feed have to be metered for the utility
thanks as always