..the change to a new 125A cost practically nada and took very little time.
On the left coast fuse boxes are buried in stucco, outside the building. Stucco cutouts must be larger than new cabinet, and can remain unpatched for months failing inspections for improper moisture-penetration barriers. EC's bid stucco patch separately, if they can even do it.

Since no listed retrofit's are possible for existing load centers, without reducing # of circuit/breakers, the low-ballers are avoiding building permis, taking the guts from new load centers and forcing them in undersized cabinets, leaving existing stucco undusturbed.
 