FRE Estimate

Alwayslearningelec

Senior Member
Location
NJ
Occupation
Estimator
Curious guys.

Have (2) 5" fiberglass duct banks with 8 conduits each. Total = 720'
Have (2) 4" fiberglass duct banks with 8 conduits each. Total = 320
Have(4) 5" fiberglass ductbanks with 2 conduits each. Total =80'

One long sweep fiberglass elbow for each run.

We also install spacers.

Ignore the sleeves between vault.


All empty and just being stubbed up within substation and dead ended where shown with extension by others later on.

Could 2 guys do the layout and install these runs in less than 3 weeks?