Lbartowski
Member
- Location
- MN
I've never had a good understanding of what exactly needs to have a 2 hour rating in a high rise.
I presume the fire pump feeder, if it can't be buried, would need a 2 hr rated assembly such as MI cable.
Would elevators require MI cable or 2 hr rated shaft if the building is fully sprinkled?
Would Emergency system feeders need to be routed in 2 hour rated shafts?
I presume the fire pump feeder, if it can't be buried, would need a 2 hr rated assembly such as MI cable.
Would elevators require MI cable or 2 hr rated shaft if the building is fully sprinkled?
Would Emergency system feeders need to be routed in 2 hour rated shafts?