Hello all, please see attached graphics illustrating a condition I ran into.
A gas pipe is ran to a standby generator by the plumber. He ran in front of a local JB and maintenance recept. I know for "equipment" that is likely to be serviced live the front work space clearance would apply. However, I do not believe a Junction box and a maintenance receptacle necessarily warrant that type of work space clearance.
Does it being a gas line add any additional considerations?
I have a funny gut feeling about it but can't necessarily point to a code section.
A gas pipe is ran to a standby generator by the plumber. He ran in front of a local JB and maintenance recept. I know for "equipment" that is likely to be serviced live the front work space clearance would apply. However, I do not believe a Junction box and a maintenance receptacle necessarily warrant that type of work space clearance.
Does it being a gas line add any additional considerations?
I have a funny gut feeling about it but can't necessarily point to a code section.