I am currently involved in a fairly large project involving the construction of a new cement plant. The electrical portion of the project comes in at about 12 million dollars for the electrical subcontractor. Thier contract is set up as such that they bill the general contractor who turns around and bills us montly based on monthly progrees payments for work completed. Every month they issue a value for the total percent of electrical work completed for the project and expect to be paid up to that certain percantage of thier overall contract.
I have been asked by the project manager to verify tha the percentage that they are claiming they have complete everymonth is accurate for the work that is actually completed in the field. I'm trying to come up with an accurate way of gauging the work completed to this point and wanted to see how others have done this similar task for such large projects.
Do you break the electrical portion down into different aspects (underground routing, equipment installation, overhead conduit, cables pulled, testing & QA/QC). This way each of these will be weighted to a certain percentage of the overall job and each can be assigned overall values with sum to the overall completion percentage.
The other possibility I thought of was breaking each area of the plant into section and assigning each complete section a weighted percentage adding to the overall completion percentage.
I'm just trying to come up with a methodical way of arriving at an accurate fair value to use for this project and ones in the future.
I have been asked by the project manager to verify tha the percentage that they are claiming they have complete everymonth is accurate for the work that is actually completed in the field. I'm trying to come up with an accurate way of gauging the work completed to this point and wanted to see how others have done this similar task for such large projects.
Do you break the electrical portion down into different aspects (underground routing, equipment installation, overhead conduit, cables pulled, testing & QA/QC). This way each of these will be weighted to a certain percentage of the overall job and each can be assigned overall values with sum to the overall completion percentage.
The other possibility I thought of was breaking each area of the plant into section and assigning each complete section a weighted percentage adding to the overall completion percentage.
I'm just trying to come up with a methodical way of arriving at an accurate fair value to use for this project and ones in the future.