brantmacga
Señor Member
- Location
- Georgia
- Occupation
- Former Child
I have a project that consists of three buildings...... I was out doing site work recently and they had set the footer steel in only two of the three buildings.
for whatever reason, they decided to just not call me when the steel was set in the third; I stopped by today to check on it and found the slabs have all been poured. GC says he didn't understand what I was talking about.......
anyway, they have 12" threaded-L's that were wet-set in the slab for tying the wall. Will it do any good whatsoever to bond to one of those? or 20?
for whatever reason, they decided to just not call me when the steel was set in the third; I stopped by today to check on it and found the slabs have all been poured. GC says he didn't understand what I was talking about.......
anyway, they have 12" threaded-L's that were wet-set in the slab for tying the wall. Will it do any good whatsoever to bond to one of those? or 20?