Hello everyone,
We are installing a new 120/208v 3800A service in a commercial building. There are no drawings or specs to go off of, more of a design build job.
The switchgear is made up of 3 sections of busbar, one service disconnect switch and two distribution panels.
We are using two of the sections of gear to land our wire. Each section will have 8 parallel feeds of 500kcmil copper conductors which makes 16 conductors per phase. So essentially 2, 3800A feeds from two utility vaults. One vault to one section, the second vault to another.
I am being told that we need to bring 2 GECs to the water pipe and 2 supplemental GECs to building steel (a set for each section).
My question is, since the sections share the same bus, A B C N and G, do we need to do this or could we just bring one GEC to the main water pipe and one supplemental GEC to building steel?
Any help is appreciated, thank you.
We are installing a new 120/208v 3800A service in a commercial building. There are no drawings or specs to go off of, more of a design build job.
The switchgear is made up of 3 sections of busbar, one service disconnect switch and two distribution panels.
We are using two of the sections of gear to land our wire. Each section will have 8 parallel feeds of 500kcmil copper conductors which makes 16 conductors per phase. So essentially 2, 3800A feeds from two utility vaults. One vault to one section, the second vault to another.
I am being told that we need to bring 2 GECs to the water pipe and 2 supplemental GECs to building steel (a set for each section).
My question is, since the sections share the same bus, A B C N and G, do we need to do this or could we just bring one GEC to the main water pipe and one supplemental GEC to building steel?
Any help is appreciated, thank you.