I don't have a lot of time so I'll keep my question simple. From what I see the Code requires a grounding electrode conductor to be installed continuous from a panel to a ground rod. If I don't get 25 ohms I have to install a second ground rod. A co-worker is telling me that if I add a second rod I have to remove the first GEC and install a new GEC that is continuous from the panel through a clamp and on to the second rod continuous without a splice. I'm telling him that the second rod is connected to the first rod with a bonding jumper and I don't have to remove the first GEC and install a new one that is continuous. all the way to the second rod Please help with any Code articles.