Can an existing GEC be spliced with a split bolt in order to get it to reach the service disconnect?
There is already a continuous GEC from the service disconnect to the newly installed ground rods.
The existing GEC that is too short ( but yet accessible enough to bug onto runs through a crawl space that’s not accessible and attaches to the incoming copper city water .
I don’t have any irreversible crimps with me.
Thanks
There is already a continuous GEC from the service disconnect to the newly installed ground rods.
The existing GEC that is too short ( but yet accessible enough to bug onto runs through a crawl space that’s not accessible and attaches to the incoming copper city water .
I don’t have any irreversible crimps with me.
Thanks