I got a two part question:
- Can you run a bare #6 GEC (waterpipe ground) through the same conduit that feeders are running through to get to the main disconnect. I thought I heard you cannot do this.
- Can the termination point of a waterpipe ground and G-rod bare #6 land under the intersystem bonding device and then just have one #6 go from the intersystem bonding device to the main disconnect? Or does each GEC need to land in the main disconnect and then drop one #6 to the intersystem boding device?