Sunny2995
Member
- Location
- North Carolina
- Occupation
- Electrical Contractor
Hello all,
Hoping for some clarification and confidence.
We have a 400A meter can, with a 400A SE rated transfer switch. Out of the transfer switch we’re feeding two 200A sub panels. The two sub panels are mounted in a metal structure. The transfer switch and meter can are on a pedestal a couple feet away. (think back to back). Here are what we have figured for this install, wanted to see what everybody’s thoughts were and if it seemed correct. For our GEC we have a #6 bare solid going from meter can to two ground rods (bonding strap provided with meter from can to neutral lug). Meter can to transfer switch with parallel 3/0 for phase conductors and neutral. Neutrals and equipment grounding conductors are bonded in transfer switch (first means of disconnect). From transfer switch we have a 1/0 going (via pvc raceway) to bond the building steel. Also from transfer switch we have two raceways feeding our 200A sub panels with a #3 EGC because of the 400A OCPD on SE transfer switch. Any clarification or thoughts would be appreciated.
T
Hoping for some clarification and confidence.
We have a 400A meter can, with a 400A SE rated transfer switch. Out of the transfer switch we’re feeding two 200A sub panels. The two sub panels are mounted in a metal structure. The transfer switch and meter can are on a pedestal a couple feet away. (think back to back). Here are what we have figured for this install, wanted to see what everybody’s thoughts were and if it seemed correct. For our GEC we have a #6 bare solid going from meter can to two ground rods (bonding strap provided with meter from can to neutral lug). Meter can to transfer switch with parallel 3/0 for phase conductors and neutral. Neutrals and equipment grounding conductors are bonded in transfer switch (first means of disconnect). From transfer switch we have a 1/0 going (via pvc raceway) to bond the building steel. Also from transfer switch we have two raceways feeding our 200A sub panels with a #3 EGC because of the 400A OCPD on SE transfer switch. Any clarification or thoughts would be appreciated.
T