Generator at Distribution Point

Status
Not open for further replies.

mattik

New User
Location
NW Minnesota
Occupation
Electrician
We have an existing service where directly after the meter we hit service distribution blocks which run multiple three wire (URD/USE cable) services to separate buildings / equipment. Each Building has a code compliant service (MBJ, GEC...). The question is does the code allow a service rated transfer switch and generator to be installed at the distribution point without having to change the cables feeding each building to a 4 wire feeder? The code I specifically am wondering if it would apply would be 250.32 (B)(1)expno.1 as when you install the Service rated transfer switch you are technically changing the existing 3- wire feeds from service conductors to feeder conductors?
 
Status
Not open for further replies.
Top