We're having a little disagreement in our office and want your opinion.
The design includes a 480/277 volt, 1200 amp service with GFP. It also includes a diesel generator that feeds two automatic transfer switches from separate output circuit breakers on the generator. One ATS is four pole with a switched neutral and it feeds a 480/277 volt life safety lighting panelboard. The other ATS is three pole with no neutral and it feeds a motor control center with only three phase 480 volt loads.
Our disagreement is whether the generator is a separately derived system and does the generator neutral get bonded to ground. My opinion is the generator is a separately derived system and the neutral must be bonded. If the neutral isn't bonded and there is a phase to ground fault the generator breaker will not operate because there is no path for the fault current to get back to the neutral point in the generator.
Another of our engineer's opinion is that when we add the three pole ATS, the generator neutral bond must be lifted. If we don't, this will create two service ground points and will be a violation of NEC.
Who is correct?
The design includes a 480/277 volt, 1200 amp service with GFP. It also includes a diesel generator that feeds two automatic transfer switches from separate output circuit breakers on the generator. One ATS is four pole with a switched neutral and it feeds a 480/277 volt life safety lighting panelboard. The other ATS is three pole with no neutral and it feeds a motor control center with only three phase 480 volt loads.
Our disagreement is whether the generator is a separately derived system and does the generator neutral get bonded to ground. My opinion is the generator is a separately derived system and the neutral must be bonded. If the neutral isn't bonded and there is a phase to ground fault the generator breaker will not operate because there is no path for the fault current to get back to the neutral point in the generator.
Another of our engineer's opinion is that when we add the three pole ATS, the generator neutral bond must be lifted. If we don't, this will create two service ground points and will be a violation of NEC.
Who is correct?