Question about the best way to layout temporary diesel generator cables from generator to load...
Scenario:
What is the best way to lay out the cables to prevent this?
Scenario:
- 2MW mobile diesel generator (480V) connected to a rental transformer (480V Delta, 12.47Wye)
- Transformer connected to electrical distribution system for summer peak shaving operations (ambient air temps >90 deg. F)
What is the best way to lay out the cables to prevent this?
- Leave a gap between ALL the cables on the ground?
- Instead of running 10 cables per phase (i.e.-10 A-phase cables next to each other, 10 B-phase cables next to each other, etc.), run the phases alternately (i.e.-ABC, ABC, ABC, etc.)?
- The total cable run between the generator & the transformer is less than or equal to 50' (we're using 50', 4/O cables)
- Cam lock connections are all good
- Connections at the generator & transformer are good