This is a 3 part question:
Question #1 What section of the code (if any) would cover the installation of a concrete "Trenya" trench and lid? This concrete trough will have 735.2 kcm (locomotive type cables) rated at 732 Amps each.
The cables will be placed in the trench from a 480V 2285 kVA generator to a 2500kVA transformer. The distance is approximately 30'.
Question #2 Should the single cables be grouped together one conductor per phase and spaced at 2.15" intervals as stated in the cable tray specifications, Articles 392.80 and 392.1(B)4?
Question #3 Should the cables be derated to 50% as per Article 310.15(B)2(a) Table, if not so grouped and spaced?
Thank you for your help.
Gregory
Question #1 What section of the code (if any) would cover the installation of a concrete "Trenya" trench and lid? This concrete trough will have 735.2 kcm (locomotive type cables) rated at 732 Amps each.
The cables will be placed in the trench from a 480V 2285 kVA generator to a 2500kVA transformer. The distance is approximately 30'.
Question #2 Should the single cables be grouped together one conductor per phase and spaced at 2.15" intervals as stated in the cable tray specifications, Articles 392.80 and 392.1(B)4?
Question #3 Should the cables be derated to 50% as per Article 310.15(B)2(a) Table, if not so grouped and spaced?
Thank you for your help.
Gregory