curt swartz
Electrical Contractor - San Jose, CA
- Location
- San Jose, CA
- Occupation
- Electrical Contractor
I have designed a generator installation for a single family dwelling. I plan to install a meter-main which will feed the utility side of an automatic transfer switch. I plan to install a circuit breaker as a service disconnect between the supply conductors of the generator and the generator side of the transfer switch. There is also a circuit breaker located in the generator installed by the manufacture. The generator is going to be located at least 100? from the equipment locations. All of this equipment is located outside The AHJ has issued comments on this design and says that I can not use the circuit breaker at the house as a disconnecting means. He says since the generator is located more than 50? from the transfer switch I must provide a listed lockable disconnect at the generator.
I don?t under why I need an additional disconnect. What purpose is there in adding an additional lockable disconnect at the generator? The service disconnect on the house will completely disconnect the generator from the house so the only portion of the circuit that will still be energized are the underground conductors from the generator. The factory installed circuit breaker in the generator will provide overload and short circuit protection. I don?t see how this installation is any different than installing a meter main on the pole then feeding a main breaker panel at the house.
Any comments would be appreciated.
I don?t under why I need an additional disconnect. What purpose is there in adding an additional lockable disconnect at the generator? The service disconnect on the house will completely disconnect the generator from the house so the only portion of the circuit that will still be energized are the underground conductors from the generator. The factory installed circuit breaker in the generator will provide overload and short circuit protection. I don?t see how this installation is any different than installing a meter main on the pole then feeding a main breaker panel at the house.
Any comments would be appreciated.