Chris3585
Member
- Location
- Smyrna, Georgia
I am designing a generator system that will serve an existing building and a new addition. The new addition is classified as a separate building and we are bringing in a separate electrical system with a neutral and a ground rod. It is my understanding that since the generator is serving multiple buildings, we have to derive a neutral at the generator and switch the neutral between the normal and generator sources.
Since we are also deriving a ground from the generator, will a parallel grounding path be created between the (2) service grounds and the generator ground?
Thanks,
Chris
Since we are also deriving a ground from the generator, will a parallel grounding path be created between the (2) service grounds and the generator ground?
Thanks,
Chris