I have a design question that I've never seen before.
We have an existing office building that we?re modifying for a client.
Currently there are two generators serving different portions of this building: a 250kW and a 500kW. We need to tap into the 500kW (utilizing a spare breaker in the genset) and run a separate feed to a new ATS to feed the portion of the building that the 250kW generator is feeding for an N+1 type configuration. The 250kW Generator is currently serving a 400A 480V Distribution board through an existing ATS and the 500kW Generator is currently serving a 800A 480V Distribution board through another existing ATS.
1) Under normal conditions, if utility is lost, the 250kW generator would run for its dedicated space through the 400A Distrubution board and the 500kW generator would run for its dedicated space through the 800A Distribution board.
2) However, if the 250kW generator does not start, or is down for maintenance, I need the 500kW generator to pick up the load that the 250kW would serve.
How would this be controlled?
I'm assuming the downstream breaker for the 500kW generator would be Normally Open on the 400A Distribution board. But where would the signal come from to close this breaker if the 250kW generator failed to start? It sounds simple, but what am I missing?
Thanks!
We have an existing office building that we?re modifying for a client.
Currently there are two generators serving different portions of this building: a 250kW and a 500kW. We need to tap into the 500kW (utilizing a spare breaker in the genset) and run a separate feed to a new ATS to feed the portion of the building that the 250kW generator is feeding for an N+1 type configuration. The 250kW Generator is currently serving a 400A 480V Distribution board through an existing ATS and the 500kW Generator is currently serving a 800A 480V Distribution board through another existing ATS.
1) Under normal conditions, if utility is lost, the 250kW generator would run for its dedicated space through the 400A Distrubution board and the 500kW generator would run for its dedicated space through the 800A Distribution board.
2) However, if the 250kW generator does not start, or is down for maintenance, I need the 500kW generator to pick up the load that the 250kW would serve.
How would this be controlled?
I'm assuming the downstream breaker for the 500kW generator would be Normally Open on the 400A Distribution board. But where would the signal come from to close this breaker if the 250kW generator failed to start? It sounds simple, but what am I missing?
Thanks!