Generator is located outside the building. It is separately derived system and they provide ground rods as grounding electrode conductor. However I am getting confused by NEC 2017 Article 250.30(C). My confusion is that should their be in addition to ground rods additional grounding electrode conductor going to building main service grounding electrode system or one grounding electrode conductor to ground rods is ok?