A number of brands of generators will now parallel with on board controls, but they have to parallel to something. I looked up bus cabinets and that brings me to a second question - why does Husky have a 3000A bus cabinet that only handles four conductors per phase up to 750MCM? I mean that isn't even one direction (source or load) - what's the point? There must be a point, right? Please explain it to me.
But my main question has to do with code requirements for multiple generators. Standard paralleling gear has a breaker per generator. The NEC says that for one generator, if the generator is within site of the building a second breaker (beyond the one that comes with the generator) is not required. Okay - so now I have three generators and the paralleling is being done with their own breakers. What does the code say? Do I need a fuse upstream of the transfer switch? Seems like I do unless I have a main breaker in my gear. I'm thinking that this configuration is correct. But do I require the fuse? What if I do have a main breaker in my MDP? Do I require a fuse then? The generator paralleling would prevent three generators from feeding the bus at once.
I am thinking that if a separate building houses the equipment, that I must have some sort of a main in the main building anyway. In that case, I particularly wouldn't want to pay for the fuse in the attached diagram.
But my main question has to do with code requirements for multiple generators. Standard paralleling gear has a breaker per generator. The NEC says that for one generator, if the generator is within site of the building a second breaker (beyond the one that comes with the generator) is not required. Okay - so now I have three generators and the paralleling is being done with their own breakers. What does the code say? Do I need a fuse upstream of the transfer switch? Seems like I do unless I have a main breaker in my gear. I'm thinking that this configuration is correct. But do I require the fuse? What if I do have a main breaker in my MDP? Do I require a fuse then? The generator paralleling would prevent three generators from feeding the bus at once.
I am thinking that if a separate building houses the equipment, that I must have some sort of a main in the main building anyway. In that case, I particularly wouldn't want to pay for the fuse in the attached diagram.