Generator

Status
Not open for further replies.

Gaffen99

Senior Member
Location
new jersey
I am looking to install a transfer switch on an existing service. The issue is the CT cabinet is integral with the switchboard. I wanted to re-route the feeders into the TS straight from the tap box but that is before the CTs. Any input or ideas? Thanks. Would the power co. relocate the CTs to the transfer switch, has this been done?
Thanks
 