Vsharp
Member
- Location
- California
- Occupation
- Journeyman electrician
I have project on a facility that has medium voltage customer owned substation feeding multiple building's with 480/277 wye. The facility was built in the 60's and very few detached building feeders have equipment grounds. The facility will soon be replacing all the substation switchgear which will require Gfpe protection per 230.95. Would the facility have to also re-pull all new equipment grounds or could either of the exemptions from 250.32(B)1 apply? There are concerns of the new ground fault protection not operating correctly.