I need some help, will this work?
2000 amp service, 480Y/277 3phase 4 wire, brought to a 2000 amp GFPE main. Properly grounded at that point, and then a 2000 amp feeder 3 wire only (with equipment ground) run to a transfer switch and then to a distribution panel which serves 3phase loads only. Some of these loads are ups systems, and they will work with or without a neutral run to them.
The generator that feeds the other side of the transfer switch is located 300' outside of the building, is a 1500kva 480Y/277 3phase 4wire system. It has a 2000 amp GFPE breaker installed at its location and then is run into the building as a 3 wire only (with equipment ground)to a disconnect and then to the transfer switch.
Question: will this work using a 3 pole transfer switch? why or why not? The transfer switch supplies optioal standby load only. Will an ups system have a nuisance trip when the transfer switch ? Thank you!
2000 amp service, 480Y/277 3phase 4 wire, brought to a 2000 amp GFPE main. Properly grounded at that point, and then a 2000 amp feeder 3 wire only (with equipment ground) run to a transfer switch and then to a distribution panel which serves 3phase loads only. Some of these loads are ups systems, and they will work with or without a neutral run to them.
The generator that feeds the other side of the transfer switch is located 300' outside of the building, is a 1500kva 480Y/277 3phase 4wire system. It has a 2000 amp GFPE breaker installed at its location and then is run into the building as a 3 wire only (with equipment ground)to a disconnect and then to the transfer switch.
Question: will this work using a 3 pole transfer switch? why or why not? The transfer switch supplies optioal standby load only. Will an ups system have a nuisance trip when the transfer switch ? Thank you!