Hi Guys,
For a typical residential service installation where the first point of disconnect is at the main panel, we typically have the customer run the water pipe ground to the panel, and have a conductor from the ground rod installed thru the meter socket, then thru the service entrance pipe and landed in the panel. In most cases, the service entrance pipe is installed into the meter socket using a concentric knockout. Therefore, a bonding bushing with jumper is required at the connection. Any issue with the GEC from the ground rod being skinned and connected to the bushing while continuing thru to the panel. I can't imagine that there is anything wrong with this, but I couldn't find anything in NEC that directly addressed it, so I figured I'd reach out for a sanity check.
Thanks,
Creig
For a typical residential service installation where the first point of disconnect is at the main panel, we typically have the customer run the water pipe ground to the panel, and have a conductor from the ground rod installed thru the meter socket, then thru the service entrance pipe and landed in the panel. In most cases, the service entrance pipe is installed into the meter socket using a concentric knockout. Therefore, a bonding bushing with jumper is required at the connection. Any issue with the GEC from the ground rod being skinned and connected to the bushing while continuing thru to the panel. I can't imagine that there is anything wrong with this, but I couldn't find anything in NEC that directly addressed it, so I figured I'd reach out for a sanity check.
Thanks,
Creig