jbreting
Member
- Location
- Lakeland, FL
- Occupation
- EE
I am designing a ground loop system for two 5000 gal tanks at a slag plant. I am restricted to how far from the tank I can place the ground wire and rods. It turns out I have to place them under the foundation the tanks are on.
Well, I am referencing some drawings from the previous engineer and he had a note: " Ground conductors that run below slab shall be installed prior to concrete pour and shall be run in 1" schedule 40 PVC conduit". Could someone tell me the reason why it needs to be ran in conduit and the NEC code that states this?
Well, I am referencing some drawings from the previous engineer and he had a note: " Ground conductors that run below slab shall be installed prior to concrete pour and shall be run in 1" schedule 40 PVC conduit". Could someone tell me the reason why it needs to be ran in conduit and the NEC code that states this?