GROUND RODS TO BE MEASURED ARE DOWN 4 FEET INTO CONCRETE TIED TO A RBAR MESH. i WILL BE DOING A 3POINT IOF POTENTIAL DROP TEST.SINCE MY CURRENT STAKE AND VOLTAGE STAKE WILL NOT PENETRATE THE CONCRETE, I HAVE TAKEN A 1FT WIDE PIECE OF FLAT BAR FOR BOTH THE STAKES TO CLIP TO. i WILL BE PUTTING WATER UNDER THE FLAT BAR TO ENSURE GOOD CONTINUITY. SHOULD THIS TYPE OF ARRANGEMENT WORK.