Stevenfyeager
Senior Member
- Location
- United States, Indiana
- Occupation
- electrical contractor
Usually I drive a ground rod when I find an old sub panel fed by 3 wires from a different building. ( from a house panel. What if there are two suboanls in sequence? First one comes underground to a private utility pole panel. Then overhead to a building panel. All existing 3 wires between each. Should I drive a ground rod at both panels? Thank you