We have an industrial customer who is having the Power Company replace a 480 volt 3 Phase 3 Wire Delta transformer with a 277/480 Volt 3 Phase 4 Wire Wye Transformer. The customer has their own Electricians, but want our Company to help them with upgrading the Service Conductors and termination. This is a Customer Owned Service from the Power Company's Transformer into the facility. Their electricians are indicating they do not need the grounded conductor ran with the phase conductors, as they do not want to increase the size of the existing conduits. We are hesitant on this installation, because we feel the grounded conductor needs to be installed in order to clear a fault. Are we correct in our interpretation? Thank you for your help!