I am installing a 120/240 v transfer switch next to a service panel on a residence for the purpose of installing a standby generator.I am running the ungrounded conductors from a 100A two pole breaker in the service panel,to the transfer switch ,and back to the service panel to tie into the sub panel feeders,in the same conduit.I have sized the conductors to allow for derateing.
My question is,do I have to run the grounded/neutural conductor from the service panel to the transfer switch and back to the service panel (two conductors)? Or will one grounded/neutural conductor between the transfer switch and the service panel meet code requirements?
My understanding is that the two ungrounded conductors running from the service panel to the transfer switch,and the two ungrounded conductors running back from the transfer switch to service panel,in the same conduit,will cancel each others magnetic fields,and I should only need the grounded/neutural conductor when the utility power is cut off or by passed and the standby generator is feeding power to the residence.Am I correct?
Thankyou for your input,
Bob.
[ February 06, 2005, 01:31 PM: Message edited by: buddog57 ]
My question is,do I have to run the grounded/neutural conductor from the service panel to the transfer switch and back to the service panel (two conductors)? Or will one grounded/neutural conductor between the transfer switch and the service panel meet code requirements?
My understanding is that the two ungrounded conductors running from the service panel to the transfer switch,and the two ungrounded conductors running back from the transfer switch to service panel,in the same conduit,will cancel each others magnetic fields,and I should only need the grounded/neutural conductor when the utility power is cut off or by passed and the standby generator is feeding power to the residence.Am I correct?
Thankyou for your input,
Bob.
[ February 06, 2005, 01:31 PM: Message edited by: buddog57 ]