Nardie
Member
- Location
- North Augusta, SC USA
So I'm installing a new 480V service to a building. At the new service entrance disconnect, the neutral and ground are bonded and then connected to the ground rod. Downstream of the service disconnect there is a 480-208/120 transformer which feeds a lighting panel. At the transformer the ground and neutral are bonded per code. All of these things I am good with. Here is my concern, all the electrical equipment is bonded together with an equipment grounding conductor. So I am concerned with creating a circulating current loop for a fault since the ground and neutral are bonded together in two different positions, and all equipment is connected via the ecg. So am I okay per code with current installation or do something different? I think I am okay, but just want to be sure. Thanks