harborrick
Member
- Location
- Irvine California
I need help on a few items.I am new to Solar.
I have a carport style arrays and have two Combiner Boxes both spread apart on 2 different columns.
I also have 2 more arrays with 1 CB box each.
We have 2 Inverters about 200 feet away on a pad. 75kw and 100kw
At CB columns I have driven a ground rod and bonded them with a #6 to Column and to CB box ground buss
From CB I have run my equipment ground back to Inverter.#8 in size to nec code.
At Inverter I have installed 1 ground rod and installed a new GEC to main service sizing wire same size as existing ground of main service (Example ,existing service 600 amp GEC 2/0 cu)
My questions is do I need to carry GEC all the way to arrays?
If so does it have to be same as service GEC
I have seen it drawn different ways from different engineers.
Thanks in advance.
I have a carport style arrays and have two Combiner Boxes both spread apart on 2 different columns.
I also have 2 more arrays with 1 CB box each.
We have 2 Inverters about 200 feet away on a pad. 75kw and 100kw
At CB columns I have driven a ground rod and bonded them with a #6 to Column and to CB box ground buss
From CB I have run my equipment ground back to Inverter.#8 in size to nec code.
At Inverter I have installed 1 ground rod and installed a new GEC to main service sizing wire same size as existing ground of main service (Example ,existing service 600 amp GEC 2/0 cu)
My questions is do I need to carry GEC all the way to arrays?
If so does it have to be same as service GEC
I have seen it drawn different ways from different engineers.
Thanks in advance.