I'm installing a remote 5 gang meter bank with 125A brk feeding each single phase 120/240 dwelling.
No main switch in bank [not required] The Poco is installing a transformer 3 feet next to meter bank.
I'm required to install 2 Gr Rods outside of vault for Poco. Can I pick up the same two Gr Rods for meter bank or not sure if I need to drive rods for bank seeing that the neutral is grounded to the 2 rods at vault.
The feeder cables will be 4 wire and each dwelling has a Cee.