K ken Member Location Alabama Jan 5, 2005 #1 With the idea of concrete encased electrodes or 2 ground rods for the house are any of the AHJ's requiring 2 rods on the temp?
With the idea of concrete encased electrodes or 2 ground rods for the house are any of the AHJ's requiring 2 rods on the temp?
P pierre Senior Member Location Westchester County, New York Jan 5, 2005 #2 Re: grounding construction temporarys Does the NEC have different service requirements for temporary or permanent installations? Where do you find them, if so? Pierre
Re: grounding construction temporarys Does the NEC have different service requirements for temporary or permanent installations? Where do you find them, if so? Pierre
George Stolz Moderator Staff member Location Windsor, CO NEC: 2017 Occupation Service Manager Jan 5, 2005 #3 Re: grounding construction temporarys NEC-2005 590.4 Services. Services shall be installed in accordance with Article 230. Click to expand...
Re: grounding construction temporarys NEC-2005 590.4 Services. Services shall be installed in accordance with Article 230. Click to expand...