I have a concrete encased electrode as per N.E.C. 250-52(A)(3) with a #4 bare copper that is connected to the neutral at the meter and also is tied to the building steel of the metal building. Our local inspecting authority has stated that because the "sole connection" is at the meter point that the building steel must comply with table 250-66, please reply.