If service entrance conductors are larger than 1100 kcmil, then the GEC needs to be 12.5% of the cross sectional area. Does this requirement only apply if ANY conductor is larger than 1100 kcmil or if the combined area is larger? In other words, do parallel sets apply to this rule where the combined area of the parallel sets exceeds 1100 kcmil.