Isaiah
Senior Member
- Location
- Baton Rouge
- Occupation
- Electrical Inspector
There's a very large (4 feet diameter), thick wall steel pipe that runs about 50' through a building. The pipe contains air only. They're installing a 3ph, 45kVA delta-wye dry-type transformer/panelboard near the pipe for temporary construction power. There are no available grounding electrodes other than two ground wells that lie about 150' away, outside building.
Construction wants to take the transformer's GEC to the pipe - i.e. bolts/footing. Although the pipe does not qualify as a grounding electrode per 250.52, construction is arguing its not unsafe and will suffice for temp power of about 3 weeks.
Any thoughts?
Construction wants to take the transformer's GEC to the pipe - i.e. bolts/footing. Although the pipe does not qualify as a grounding electrode per 250.52, construction is arguing its not unsafe and will suffice for temp power of about 3 weeks.
Any thoughts?