how is grounding of i beams and tanks acomplished in buildings ?
there is a 600 amp. 3 phase 240 volt 3-wire service to the building and i was asked to check the grounds to the building steel and have no idea how that is done.
it 's a very old plant and i don't see any signs of a ground system or ground rods. i like to know how ground some holding tanks.
thanks for any help guys.
storage tanks contain all types of products including flamable products and this one contains a type of alcohol . i think should be grounded. thanks again
there is a 600 amp. 3 phase 240 volt 3-wire service to the building and i was asked to check the grounds to the building steel and have no idea how that is done.
it 's a very old plant and i don't see any signs of a ground system or ground rods. i like to know how ground some holding tanks.
thanks for any help guys.
storage tanks contain all types of products including flamable products and this one contains a type of alcohol . i think should be grounded. thanks again