well ,kind of.
(05NEC) have a single overhead service, split to 3 @100A panels. (triplex)
panels are side -by- side.
all ground to nuetral bond bars are in place and landed.
contractor ran #6 solid from one ground bar, to the next ground bar, to the next ground bar.
then ran a #4 solid (from the "last" panel ) to the uffer.
is this creating some sort of parallel path for faults (either nuetral or ground)?
can't wrap my hands around the violation, but i'm sure it's there...
(05NEC) have a single overhead service, split to 3 @100A panels. (triplex)
panels are side -by- side.
all ground to nuetral bond bars are in place and landed.
contractor ran #6 solid from one ground bar, to the next ground bar, to the next ground bar.
then ran a #4 solid (from the "last" panel ) to the uffer.
is this creating some sort of parallel path for faults (either nuetral or ground)?
can't wrap my hands around the violation, but i'm sure it's there...